Add to Cart
Battery Operated Steel Coil Transfer Truck in Heavy Industry Manufacturing
The Trolley is Battery powered. It comes in lengths of 4000, 4500 or 5000 mm and widths of 2200 or 2500mm. Larger Warehouse Cargo Trolley capacities and sizes are available for specific applications. Our Trolley loads up to 300 tons. They can be also AC powered or diesel propulsion type. Custom deck frames can be designed for specific assemblies to carry an entire shift of production and even serve as a stable movable machine base.
Model | BXC-2T | BXC-10T | BXC-20T | BXC-30T | BXC-50T | BXC-63T | BXC-150T | |
Rated load (T) | 2 | 10 | 20 | 30 | 50 | 63 | 150 | |
Table size | length(L) | 2000 | 3600 | 4000 | 4500 | 5500 | 5600 | 10000 |
Width(W) | 1500 | 2000 | 2200 | 2200 | 2500 | 2500 | 3000 | |
Height(H) | 450 | 500 | 550 | 600 | 650 | 700 | 1200 | |
Wheel Base (mm) | 1200 | 2600 | 2800 | 3200 | 4200 | 4300 | 7000 | |
Wheel Diameter(mm) | Φ270 | Φ300 | Φ350 | Φ400 | Φ500 | Φ600 | Φ600 | |
Ground Clearance (mm) | 50 | 50 | 50 | 50 | 50 | 75 | 75 | |
Motor Power (Kw) | 1 | 1.6 | 2.2 | 3.5 | 5 | 6.3 | 15 |
Production & Processing
CNC Cutting Transport the steel plate from raw material warehouse to CNC cutting workshop for cutting. After the cutting, the workers will do some simple processing such as chip moving and setting out.
Preliminary Assembling
Put the cut steel plate together according to the design drawing
Welding Weld the steel plate with automatic welding machine after the preliminary assembling
Post weld treatment Test the welding section after the welding, polish and burring. Post weld treatment to eliminate welding stress
Spray Primer Transport the structure part after processing to painting booth for spraying primer. The main component of the primer is zinc rich epoxy antirust paint. The primer is to two layers
Assembling Assemble the structure parts after spraying primer with wheels, motors, and gearbox, etc.
Paint finish Transport the assembled cart to painting booth, inspect the integrity of the primer. After that paint the finish
Debugging the cart after painting the finish with the electric control system, after the debugging, the cart will test without load. And after the no-load test, the cart will be tested with the load. After the inspection, the cart will be transported to the storage area.